benching sloping ground to

trench, bench and slope safety - for construction pros

'slfs can be used for slope grading,' he adds, 'if the machine is sitting flat on the ground and the operator can pull the grade to him.' providing a stable platform for the excavator is an

excavation safety: sloping and benching - virginia tech

specifications for sloping and benching, when used as methods of protecting employees working in excavations from cave-ins, are provided in this section. definitions. actual slope means the slope to which an excavation face is excavated. distress means that the soil is in a condition where a cave-in is imminent or is likely to occur. distress

osha technical manual otm section v: chapter 2

unit weight of soils refers to the weight of one unit of a particular soil. the weight of soil varies with type and moisture content. one cubic foot of soil can weigh from 110 pounds to 140 pounds or more, and one cubic meter 35.3 cubic feet of soil can weigh more than 3,000 pounds.

standards for keying and benching of embankments

sloping ground, especially in expansive soils and slopes floored in siltstone or shale, because this zone serves as a conduit for percolating water.

geotechnical bulletin - pages

the back slope of each bench is cut at a typical 1h:1v slope. this slope may need to be flattened based on the short term stability of the soils in the existing slope. if the existing slope is made up primarily of granular materials, a slope approaching 30 approximately 1.75 h:1v may be more appropriate.

trench, bench and slope safety - for construction pros

login or register now to gain instant access to the rest of this seven trust content improper operation of an excavator while trenching, sloping or benching can have a big impact on productivity and can potentially place both people and equipment at risk. oftentimes, it's the result of poor or inadequate training.

back to basics: sloping and benching - utility contractor

back to basics: sloping and benching. osha requires type c soil to be sloped at 1½h:1v and it cannot be benched. this means that the slope must be cut back 1½ ft horizontally for every 1 ft of depth. the 1½:1 is equal to an angle of 34 degrees from the horizontal. as for type a soil, the slope must be ¾h:1v, or 53 degrees, and type b soil,

buildsum: benching, battering and shoring

benching the excavation is cut in a series of steps. each step should not be deeper than 1.5m and it should be set back enough so that if the top level was to collapse it would not fall into the bottom of the trench.

excavation safety: sloping and benching - virginia tech

specifications for sloping and benching, when used as methods of protecting employees working in excavations from cave-ins, are provided in this section. definitions. actual slope means the slope to which an excavation face is excavated. distress means that the soil is in a condition where a cave-in is imminent or is likely to occur. distress is evidenced by such phenomena as the development of fissures in the face of or adjacent to an open excavation; the subsidence of the edge of an

excavation: general remarks - construction technology

the last class, 'benching sloping ground to receive filling', relates to the practice of excavating a permanent unsupported side slope down which there are horizontal steps which, when filled over with imported material, prevent that material slumping to the bottom of the excavation.

excavations - oregon

sloping, benching, shoring, and shielding. the method you should use depends on factors such as soil type and water content, excavation depth and width, the nature of the work, and nearby activities that could increase the risk of a cave-in. the competent person has the responsibility for considering

sloping and benching systems

appendix b ­ simple sloping systems for type a soil for type a soil and a trench depth of less than 20 feet, the steepest maximum allowable slope is 53 degrees from the horizontal. this translates to a 0.75h: 1v incline and is shown below. maximum allowable slope

trenching and shoring guidelines

slope and shield configurations. sloping and benching sloping maximum allowable slopes for excavations less than 20 ft 6.09 m based on soil type and angle to the horizontal are as follows: allowable slopes. soil type height/depth ratio slope angle stable rock vertical 90 type a ¾:1 53 type b 1:1 45 type c 1½:1 34

how to build bench on sloped land

to create seating using a sloped outdoor area for an amphitheater or chapel in the woods or backyard theater, the easiest type of bench to use is a simple plank bench bench terraces - fao

terracing and leveling a sloping garden, services and diy

scroll down for tips to level a slope. terracing or leveling a sloping garden adds interest and creates workable space, allowing planting at different levels, maybe flower borders and a patio on the top terrace and a vegetable patch lower down the slope, with a herb garden near the kitchen.

modulus 13 quiz flashcards quizlet

benching system safety net. osha has approved sloping, shoring, and benching to be used as safety systems in which one of these jobs? road paving when the height of workplaces exceeds 30 feet above ground, what safety device must be provided for workers? guardrails personal fall protection

1926 subpart p app b - sloping and benching occupational

the requirements of this appendix apply when the design of sloping and benching protective systems is to be performed in accordance with the requirements set forth in § 1926.652 b 2 . b definitions. actual slope means the slope to which an excavation face is excavated.

appendix b - sloping and benching - excavation - subpart p

appendix b - sloping and benching. the maximum allowable slope for a soil or rock deposit shall be determined from table b-1 of this appendix. if that situation occurs, the slope shall be cut back to an actual slope which is at least ½ horizontal to one vertical ½h:1v less steep than the maximum allowable slope.